Roadworks at Steps Bridge update

We have been informed by Devon County Council Highways that they are currently in the process of rescheduling the repair work at Steps Bridge, Dunsford Woods.

The scope of the works will include two phases of road closures:

Phase 1 – Preliminary works – vegetation clearance and tree cutting.

This phase is scheduled to commence at the end of October and will last for up to two weeks, from Monday 20th October to 10th November 2025.

Phase 2 – Main works – carriageway stabilisation and the reinstatement of safety barriers.

The work is scheduled for early next year, starting from Monday 5th January 2026 and is expected to last for 16 weeks.

We will share any further updates as we receive them.